Anniston, AL – Jackson Hodges, Anniston Public Relations Director, shared that crosswalk improvements will be made this month at the intersections of 11th Street and Noble Street. The work is scheduled to take place as follows:
-
Week 1 – 6/5/23 – 6/9/23
-
Week 2 – 6/12/23 – 6/16/23
-
Week 4 – 6/26/23 – 6/30/23
Work on the crosswalk colored in blue will begin this week from June 6th to June 9th. Work on the crosswalk colored in green will occur from June 12th to June 16th. Work on the two Noble Street crosswalks, colored in red, will occur from June 26th to June 30th.
During each of these weeks, the crossing listed for work will be closed. Thus, traffic will not be able to pass through that week’s listed crossing.