Anniston, AL – Public Relations Director for the city of Anniston, Jackson Hodges, released a transit alert for rail road crossing closures. Please be aware of multiple railroad crossing closures that will be occurring from Tuesday, Dec. 20, 2022 through Thursday, Dec. 22, 2022.
Please note, the following schedule is tentative and some dates may change. Each closure is expected to last for 3-4 hours and work is expected to begin around 8:00 AM CT each day.
- Street: Fish Hatchery Ln, Eastaboga, Alabama 36260
- Date: Tuesday, Dec. 20, 2022
- Location of Closure: https://goo.gl/maps/nnCoPJRr6LmszZoTA
- Street: Craig Drive, Anniston, AL 36201
- Date: Tuesday, Dec. 20, 2022
- Location of Closure: https://goo.gl/maps/EMAc5ZXoJ3Uhc8p17
- Street: Willingham Drive, Anniston, AL 36201
- Date: Tuesday, Dec. 20, 2022
- Location of Closure: https://goo.gl/maps/Ygqb9adHPFDH7UBK7
- Street: Virginia Avenue N, Anniston, AL 36201
- Date: Wednesday, Dec. 21, 2022
- Location of Closure: https://goo.gl/maps/iuK3AMLcydojfYoq6
- Street: West Park Drive, Anniston, AL 36201
- Date: Wednesday, Dec. 21, 2022
- Location of Closure: https://goo.gl/maps/5hYUjoQz1eCashjr6
- Street: Tillman Avenue, Anniston, AL 36201
- Date: Wednesday, Dec. 21, 2022
- Location of Closure: https://goo.gl/maps/3kXGL3LHYfcETaf28
- Street: Pinson Road, Anniston, AL 36201
- Date: Thursday, Dec. 22, 2022
- Location of Closure: https://goo.gl/maps/QP8hg1AWv8VuU9aG8
- Street: Cooper Circle, Anniston, AL 36201
- Date: Thursday, Dec. 22, 2022
- Location of Closure: https://goo.gl/maps/1Xh8meXDPnHsjg5Y6
Lastly, additional crossing work will then take place in early January 2023 at these sites, and at that time these crossings will be closed for multiple days. A separate transit alert will be issued for the January 2023 work at a later date.
Those with questions may contact Andrea Janka, with Norfolk Southern, at: 419-615-9923.